Sweetwater 1 substation energization

Company: IREN - Project: Sweetwater 1

Subject kind
facility timeline
Statement date
2025-11-05
Promised by
2026-04-30
Promised amount
1400.0 MW
Current status
verified

What the later record shows

Delivered on time

On the Q3 FY26 earnings call (transcript dated 2026-05-10, results released 2026-05-07), IREN said the Sweetwater 1 high-voltage substation had been energized 'on schedule', and later articles confirm it was energized earlier in 2026. No passage gives the exact date, and the February 10-Q had widened the target to Q2 2026, so it cannot be confirmed that energization was by 30 April rather than in early May.

“a substation energization date in the second quarter of calendar year 2026 for Sweetwater 1”
2026-02-04 · IREN 10-Q filed 2026-02-05 View cached copy (2026-08-31)Live source ↗
“At Sweetwater 1, the high- voltage substation has been energized on schedule and construction is now underway for the initial 200 megawatts IT load phase”
2026-05-10 · iren 8-K exhibit (irentranscript.htm) View cached copy (2026-09-07)Live source ↗
“At Sweetwater 1, IREN energized its high-voltage substation earlier this year.”
2026-09-14 · IREN shares stabilize as $1 billion ARR offsets AI slowdown fears - scanx.trade View cached copy (2026-09-20)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

IREN is targeting energization of the Sweetwater 1 substation (1,400MW capacity) in April 2026.

Source (primary)

iren 8-K exhibit (q1fy26resultspressreleas.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-27)Live source ↗

Quote: “Sweetwater 1 (1,400MW) substation energization targeting April 2026”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

IREN's Q1 FY26 results release lists Sweetwater 1 (1,400MW) with substation energization targeting April 2026.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000187884825000079/q1fy26resultspressreleas.htm) in full (25,079 characters, retrieved September 27, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms iren 8-K exhibit (q1fy26resultspressreleas.htm)

Quote: “Sweetwater 1 (1,400MW) substation energization targeting April 2026”

View cached copy (2026-09-27)Live source ↗

confirms IREN 10-Q filed 2026-02-05

Quote: “a substation energization date in the second quarter of calendar year 2026 for Sweetwater 1”

View cached copy (2026-08-31)Live source ↗

confirms iren 8-K exhibit (irentranscript.htm)

Quote: “At Sweetwater 1, the high- voltage substation has been energized on schedule and construction is now underway for the initial 200 megawatts IT load phase”

View cached copy (2026-09-07)Live source ↗

confirms IREN shares stabilize as $1 billion ARR offsets AI slowdown fears - scanx.trade

Quote: “At Sweetwater 1, IREN energized its high-voltage substation earlier this year.”

View cached copy (2026-09-20)Live source ↗

Record of changes

September 27, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 27, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.