Abernathy Campus initial and expansion capacity

Company: TeraWulf - Project: Abernathy HPC Campus

Subject kind
facility capacity
Statement date
2025-11-09
Promised amount
240.0 MW
Current status
stated

The claim, verbatim

Abernathy Campus is initially designed for 240 MW of capacity with potential site expansion to 600 MW

Source (primary)

terawulf 8-K exhibit (a_wulfformearningsreleaseq.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-27)Live source ↗

Quote: “The Abernathy Campus is initially designed for 240 MW of capacity with potential site expansion to 600 MW”

How we checked this

Checked on September 29, 2026. The cited source supports every part of this claim.

The release states that the Abernathy Campus is initially designed for 240 MW with potential site expansion to 600 MW.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330125000096/a_wulfformearningsreleaseq.htm) in full (25,617 characters, retrieved September 27, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (a_wulfformearningsreleaseq.htm)

Quote: “The Abernathy Campus is initially designed for 240 MW of capacity with potential site expansion to 600 MW”

View cached copy (2026-09-27)Live source ↗