High investment grade hyperscaler 810 MW leases across two regions
Company: Applied Digital
The claim, verbatim
Signed leases with high investment grade hyperscaler across two separate regions for combined 810 MW critical IT load
Source (primary)
Five leases lifted Applied Digital (APLD)'s initial-term contracted revenue beyond $7 billion. - Stock Titan (-, news_article)
View cached copy (2026-09-26)Live source ↗Archive.org ↗
Quote: “signed leases with a high investment grade hyperscaler across two separate regions of the country for a combined 810 MW of critical IT load”
How we checked this
Checked on September 28, 2026. The cited source supports every part of this claim.
The CEO letter in the proxy states the company signed leases with a high investment grade hyperscaler across two separate regions for a combined 810 MW of critical IT load, and the CD&A repeats the 810 MW figure.
Confirmed in the source:
- Applied Digital signed leases with a high investment grade hyperscaler
- The leases span two separate regions of the country
- The leases total a combined 810 MW of critical IT load
What we did: Read our cached copy of the publisher (https://www.stocktitan.net/sec-filings/APLD/def-14a-applied-digital-corp-definitive-proxy-statement-295e8d7c8256.html) in full (290,241 characters, retrieved September 26, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Five leases lifted Applied Digital (APLD)'s initial-term contracted revenue beyond $7 billion. - Stock Titan
Quote: “signed leases with a high investment grade hyperscaler across two separate regions of the country for a combined 810 MW of critical IT load”