The claim, verbatim

CleanSpark will provide completion guarantee for Sandersville Facility and will fund the issuer as necessary to ensure timely completion if note proceeds and available funds are insufficient

Source (primary)

CleanSpark Closes $2.276B Senior Secured Notes for Georgia Data Center - Unite.AI (-, news_article)
View cached copy (2026-09-26)Live source ↗Archive.org ↗

Quote: “CleanSpark will provide a customary completion guarantee for the Sandersville Facility, under which it will fund the issuer as necessary to ensure timely completion of the facility if the note proceeds and available funds, including CleanSpark's prior equity contributions relating to the facility, are insufficient.”

How we checked this

Checked on September 28, 2026. The cited source supports every part of this claim.

The article, citing the 8-K, describes CleanSpark's customary completion guarantee in these terms.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.unite.ai/cleanspark-closes-2-276b-senior-secured-notes-for-georgia-data-center/) in full (10,004 characters, retrieved September 26, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark Closes $2.276B Senior Secured Notes for Georgia Data Center - Unite.AI

Quote: “CleanSpark will provide a customary completion guarantee for the Sandersville Facility, under which it will fund the issuer as necessary to ensure timely completion of the facility if the note proceeds and available funds, including CleanSpark's prior equity contributions relating to the facility, are insufficient.”