Dalton, GA facility initial delivery

Company: Core Scientific

Subject kind
facility timeline
Statement date
2026-09-26
Promised by
2027-12-31
Current status
stated

The claim, verbatim

Dalton, GA facility estimated initial delivery in second half of 2027

Source (primary)

Second Quarter Fiscal Year 2026 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-26)Live source ↗

Quote: “Dalton, GA Est. 2H 2027 initial delivery”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Second Quarter Fiscal Year 2026 Earnings Presentation

Quote: “Dalton, GA Est. 2H 2027 initial delivery”

View cached copy (2026-09-26)Live source ↗