New power contract at existing site

Company: Core Scientific

Subject kind
partnership
Statement date
2025-10-30
Promised by
2025-12-31
Promised amount
1.0 contract
Current status
verified

What the later record shows

Delivered; the record does not say when

The Q4 2025 results release (March 2, 2026) reports ~300 MW of added gross power capacity at the existing Dalton and Pecos sites. It does not say when the contracts were signed.

“Power Expansion at Existing Locations : Increased gross power capacity by ~300 MW across Dalton, Georgia and Pecos, Texas.”
2026-03-01 · core-scientific 8-K exhibit (q42025corescientificinc-ea.htm) View cached copy (2026-09-13)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Expects one or more new power contract(s) at existing site(s) by Q4 2025

Source (primary)

Investor Conference Call Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-26)Live source ↗

Quote: “One or more new power contract(s) at existing site(s)”

How we checked this

Checked on October 12, 2026. The cited source supports part of this claim, but not all of it.

The presentation lists new power contracts at existing sites under 'What to expect by Q4 earnings', which is a later milestone than the end of Q4 2025 stated in the claim.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_fda3a1f2f1890adaa7ac6c4d9d310971/corescientific/db/1066/11263/pdf/Core+Scientific+Investor+Update+Presentation+FINAL.pdf) in full (11,378 characters, retrieved September 26, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Investor Conference Call Presentation

Quote: “One or more new power contract(s) at existing site(s)”

View cached copy (2026-09-26)Live source ↗

confirms core-scientific 8-K exhibit (q42025corescientificinc-ea.htm)

Quote: “Power Expansion at Existing Locations : Increased gross power capacity by ~300 MW across Dalton, Georgia and Pecos, Texas.”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 26, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 27, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-26 was the source's retrieval date; source published 2025-10-30.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.