250 MW energization by end 2025
Company: Core Scientific
What the later record shows
Delivered; the record does not say when
By March 2, 2026 the company reported ~350 MW energized, which exceeds 250 MW. No passage says whether 250 MW was reached by December 31, 2025.
“Continued Execution on CoreWeave Contract: To date, energized ~350 MW of power and remain on track to deliver ~590 MW by early 2027.”
2026-03-01 · core-scientific 8-K exhibit (q42025corescientificinc-ea.htm) View cached copy (2026-09-13)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
On track to energize 250 MW by the end of 2025
Source (primary)
Investor Conference Call Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-26)Live source ↗
Quote: “On track to energize 250 MW by the end of 2025 and a total of 590 MW by early 2027”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The presentation states the company is on track to energize 250 MW by the end of 2025.
Confirmed in the source:
- Core Scientific says it is on track to energize 250 MW by the end of 2025
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_fda3a1f2f1890adaa7ac6c4d9d310971/corescientific/db/1066/11263/pdf/Core+Scientific+Investor+Update+Presentation+FINAL.pdf) in full (11,378 characters, retrieved September 26, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Investor Conference Call Presentation
Quote: “On track to energize 250 MW by the end of 2025 and a total of 590 MW by early 2027”
confirms core-scientific 8-K exhibit (q42025corescientificinc-ea.htm)
Quote: “Continued Execution on CoreWeave Contract: To date, energized ~350 MW of power and remain on track to deliver ~590 MW by early 2027.”