Early 2027 Cumulative Capacity Target
Company: Core Scientific
The claim, verbatim
Total of approximately 590 MW of colocation capacity to be delivered by early 2027
Source (primary)
First Quarter Fiscal Year 2025 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-26)Live source ↗
Quote: “And a total of ~590 MW by early 2027”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The presentation states the company expects a total of ~590 MW by early 2027 and breaks that down as estimated contracted high-density colocation MW by site.
Confirmed in the source:
- Core Scientific targets a total of approximately 590 MW of delivered capacity by early 2027
- The ~590 MW total is high-density colocation capacity
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_fda3a1f2f1890adaa7ac6c4d9d310971/corescientific/db/1066/11247/pdf/First+Quarter+Fiscal+Year+2025+Earnings+Presentation.pdf) in full (28,649 characters, retrieved September 26, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms First Quarter Fiscal Year 2025 Earnings Presentation
Quote: “And a total of ~590 MW by early 2027”