Available HPC hosting capacity
Company: Core Scientific
The claim, verbatim
Over 100 MW critical IT load available to contract
Source (primary)
December 2024 Convertible Note Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-26)Live source ↗Archive.org ↗
Quote: “Over 100 MW critical IT load available to contract”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The presentation states 'Over 100 MW critical IT load available to contract' in its 12/1/24 capacity overview, with a footnote that the figure is an estimate.
Confirmed in the source:
- Core Scientific reported over 100 MW of critical IT load available to contract (as of 12/1/24, described as an engineering estimate subject to change)
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_fda3a1f2f1890adaa7ac6c4d9d310971/corescientific/db/1066/11131/pdf/Core_Scientific_December_2024_Company_Presentation.pdf) in full (23,998 characters, retrieved September 26, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms December 2024 Convertible Note Presentation
Quote: “Over 100 MW critical IT load available to contract”