ASDC 5 - 112 MW HPC delivery

Company: Core Scientific

Subject kind
facility timeline
Statement date
2024-08-07
Promised by
2026-06-30
Promised amount
112.0 MW
Current status
outcome unconfirmed

What the later record shows

Outcome not yet confirmed

Passages confirm the 112 MW option was exercised, but none refers to ASDC 5 or reports delivery of that capacity in the first half of 2026.

“on August 6, 2024, CoreWeave exercised an option to secure an additional 112 MW of infrastructure”
2025-09-25 · Core Scientific DEFM14A filed 2025-09-26 View cached copy (2026-08-31)Live source ↗

Checked November 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

112 MW of HPC infrastructure delivery in H1 2026 for ASDC 5

Source (primary)

Second Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-26)Live source ↗

Quote: “H1 2026 112MW Delivery ASDC 5”

How we checked this

Checked on October 12, 2026. The cited source supports part of this claim, but not all of it.

The timeline chart lists ASDC 5 fifth with 112 MW. The extracted chart does not show which half-year each delivery falls in.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_fda3a1f2f1890adaa7ac6c4d9d310971/corescientific/db/1066/11129/pdf/Core_Scientific_Q2_2024_Earnings_Presentation.pdf) in full (24,266 characters, retrieved September 26, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Second Quarter Fiscal Year 2024 Earnings Presentation

Quote: “H1 2026 112MW Delivery ASDC 5”

View cached copy (2026-09-26)Live source ↗

Record of changes

September 26, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 27, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-26 was the source's retrieval date; source published 2024-08-07.