ASDC 1 - 80 MW HPC delivery
Company: Core Scientific
What the later record shows
Outcome not yet confirmed
No passage mentions ASDC 1 or an 80 MW HPC delivery in H2 2024, and none ties ASDC 1 to a named site.
Checked November 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
80 MW of HPC infrastructure delivery in H2 2024 for ASDC 1
Source (primary)
Second Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-26)Live source ↗
Quote: “H2 2024 80MW Delivery ASDC 1”
How we checked this
Checked on October 12, 2026. The cited source supports part of this claim, but not all of it.
The timeline chart lists five data center deliveries totaling 382 MW in order, so the 80 MW figure for ASDC 1 is supported. The extracted chart shows four half-year periods for five deliveries and does not show which period each delivery falls in.
Confirmed in the source:
- The 382 MW HPC delivery timeline lists ASDC 1 with an 80 MW delivery
We could not confirm this from the cited source:
- ASDC 1's 80 MW delivery is scheduled for H2 2024
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_fda3a1f2f1890adaa7ac6c4d9d310971/corescientific/db/1066/11129/pdf/Core_Scientific_Q2_2024_Earnings_Presentation.pdf) in full (24,266 characters, retrieved September 26, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Second Quarter Fiscal Year 2024 Earnings Presentation
Quote: “H2 2024 80MW Delivery ASDC 1”