Additional sites 600MW+ capacity before end of 2022
Company: Applied Digital
What the later record shows
Partly delivered
The only additional site evidenced is the 180MW Ellendale, North Dakota facility, built after August 2022. No other states' sites appear, so the 600MW, three-site plan was only partly met.
“Applied Digital’s third co-hosting facility is in Ellendale, North Dakota with planned capacity of 180MW.”
2023-01-09 · Earnings Release View cached copy (2026-10-23)Live source ↗Archive.org ↗
“The Company took possession of the land on August 15, 2022, built a hosting facility, and began energizing the site on March 4, 2023.”
2024-05-05 · Applied Digital 424B5 filed 2024-05-06 View cached copy (2026-08-31)Live source ↗
Checked November 8, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Plans to be in construction on up to three sites in three states including North Dakota with combined capacity over 600MW before end of calendar 2022
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-25)Live source ↗Archive.org ↗
Quote: “plans to be in construction on up to three other sites in three other states, including North Dakota, with total combined capacity of over 600MW before the end of calendar 2022”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The release states the plan for up to three other sites in three other states, including North Dakota, totaling over 600MW, before the end of calendar 2022.
Confirmed in the source:
- The company planned to be in construction on up to three other sites in three other states
- North Dakota was among those states
- The sites' total combined capacity would be over 600MW
- Construction was planned to be under way before the end of calendar 2022
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/10/applied-blockchain-reports-fiscal-third-quarter-2022-ended/) in full (19,893 characters, retrieved September 25, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “plans to be in construction on up to three other sites in three other states, including North Dakota, with total combined capacity of over 600MW before the end of calendar 2022”