Lake Hawkeye critical IT load capacity
Company: TeraWulf - Project: Lake Hawkeye
The claim, verbatim
Lake Hawkeye could support approximately 320 megawatts of critical IT load
Source (primary)
TeraWulf CEO Moves to Monetize 3 Million Shares Tied to Land Lease - TheEnergyMag (-, news_article)
View cached copy (2026-09-24)Live source ↗
Quote: “or 320 megawatts of critical IT load”
How we checked this
Checked on September 27, 2026. The cited source supports every part of this claim.
The source reports TeraWulf's statement that the site could support 320 MW of critical IT load, subject to permitting and development.
Confirmed in the source:
- TeraWulf said the Lake Hawkeye site could support approximately 320 megawatts of critical IT load
What we did: Read our cached copy of the publisher (https://www.theenergymag.com/news/market-news/terawulf-prager-forward-sale-3-million-ai-hpc-land-lease) in full (5,314 characters, retrieved September 24, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms TeraWulf CEO Moves to Monetize 3 Million Shares Tied to Land Lease - TheEnergyMag
Quote: “or 320 megawatts of critical IT load”