River Bend expansion capacity ROFO for Fluidstack
Company: Hut 8 - Project: River Bend
The claim, verbatim
Fluidstack holds a right of first offer for up to 1,000 MW of additional IT capacity at River Bend, subject to power expansion
Source (primary)
hut-8 8-K exhibit (hut-20251217xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-23)Live source ↗
Quote: “Right of first offer (ROFO) for up to 1,000 MW of additional IT capacity, subject to power expansion at the site”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms hut-8 8-K exhibit (hut-20251217xex99d2.htm)
Quote: “Right of first offer (ROFO) for up to 1,000 MW of additional IT capacity, subject to power expansion at the site”