River Bend initial utility capacity

Company: Hut 8 - Project: River Bend

Subject kind
facility capacity
Statement date
2025-12-16
Promised amount
330.0 MW
Current status
stated

The claim, verbatim

River Bend will have 330 MW of initial utility capacity

Source (primary)

hut-8 8-K exhibit (hut-20251217xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-23)Live source ↗

Quote: “330 MW utility capacity with 1.35 PUE”

How we checked this

Checked on September 26, 2026. The cited source supports every part of this claim.

The document lists 330 MW of utility capacity with a 1.35 PUE, and separately lists Initial Utility Capacity of 330 MW.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1964789/000110465925122052/hut-20251217xex99d2.htm) in full (23,132 characters, retrieved September 23, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms hut-8 8-K exhibit (hut-20251217xex99d2.htm)

Quote: “330 MW utility capacity with 1.35 PUE”

View cached copy (2026-09-23)Live source ↗