River Bend initial utility capacity
Company: Hut 8 - Project: River Bend
The claim, verbatim
River Bend will have 330 MW of initial utility capacity
Source (primary)
hut-8 8-K exhibit (hut-20251217xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-23)Live source ↗
Quote: “330 MW utility capacity with 1.35 PUE”
How we checked this
Checked on September 26, 2026. The cited source supports every part of this claim.
The document lists 330 MW of utility capacity with a 1.35 PUE, and separately lists Initial Utility Capacity of 330 MW.
Confirmed in the source:
- River Bend has 330 MW of initial utility capacity
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1964789/000110465925122052/hut-20251217xex99d2.htm) in full (23,132 characters, retrieved September 23, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms hut-8 8-K exhibit (hut-20251217xex99d2.htm)
Quote: “330 MW utility capacity with 1.35 PUE”