Entergy utility power capacity for River Bend
Company: Hut 8 - Project: River Bend
The claim, verbatim
Hut 8 secured initial 330 MW utility capacity from Entergy Louisiana with potential to scale by up to additional 1,000 MW utility capacity
Source (primary)
hut-8 8-K exhibit (hut-20251217xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-23)Live source ↗
Quote: “Hut 8 secured an initial 330 MW of utility capacity for the campus, supporting the initial River Bend lease, with the potential to scale by up to an additional 1,000 MW of utility capacity”
How we checked this
Checked on September 26, 2026. The cited source supports every part of this claim.
The release states that, working with Entergy Louisiana, Hut 8 secured an initial 330 MW with potential to add up to 1,000 MW.
Confirmed in the source:
- Hut 8 secured an initial 330 MW of utility capacity for River Bend, working with Entergy Louisiana
- The utility capacity could scale by up to an additional 1,000 MW
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1964789/000110465925122052/hut-20251217xex99d1.htm) in full (19,971 characters, retrieved September 23, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms hut-8 8-K exhibit (hut-20251217xex99d1.htm)
Quote: “Hut 8 secured an initial 330 MW of utility capacity for the campus, supporting the initial River Bend lease, with the potential to scale by up to an additional 1,000 MW of utility capacity”