Credit facility closure expected in early Q1 2026

Company: WhiteFiber

Subject kind
financing
Statement date
2025-12-17
Promised by
2026-03-31
Current status
verified

What the later record shows

Delivered late · happened April 27, 2026

The first credit facility recorded after the target is an amended RBC credit agreement dated April 27, 2026, which falls after Q1. No passage confirms that this is the facility the company referred to in December 2025.

“On April 27, 2026, the Company entered into an amended credit agreement with RBC. This agreement replaces the original credit agreement dated June 18, 2025”
2026-05-13 · WhiteFiber 10-Q filed 2026-05-14 View cached copy (2026-08-31)Live source ↗

Checked November 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

WhiteFiber expects to formalize a credit facility in early Q1 2026

Source (primary)

whitefiber 8-K exhibit (ea026991801ex99-1_white.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-23)Live source ↗

Quote: “The Company expects to formalize a credit facility in early Q1 2026”

How we checked this

Checked on November 10, 2026. The cited source supports every part of this claim.

WhiteFiber's December 18, 2025 press release states the company expects to formalize a credit facility in early Q1 2026, which matches the claim exactly.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/2042022/000121390025123321/ea026991801ex99-1_white.htm) in full (8,218 characters, retrieved September 23, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms whitefiber 8-K exhibit (ea026991801ex99-1_white.htm)

Quote: “The Company expects to formalize a credit facility in early Q1 2026”

View cached copy (2026-09-23)Live source ↗

confirms WhiteFiber 10-Q filed 2026-05-14

Quote: “On April 27, 2026, the Company entered into an amended credit agreement with RBC. This agreement replaces the original credit agreement dated June 18, 2025”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 23, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 24, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.