Sandersville facility construction and rent commencement

Company: CleanSpark - Project: Sandersville

Subject kind
facility timeline
Statement date
2026-09-17
Promised by
2028-03-31
Current status
stated

The claim, verbatim

Rent will begin November 30, 2027, after completion of the first network hall, with construction expected to finish in March 2028

Source (primary)

CleanSpark Names Meta as Tenant Behind $6.6 Billion Data Center Lease - TheEnergyMag (-, news_article)
View cached copy (2026-09-21)Live source ↗

Quote: “The financing presentation projects rent beginning Nov. 30, 2027, after completion of the first network hall, with construction expected to finish in March 2028”

How we checked this

Checked on September 26, 2026. The cited source supports part of this claim, but not all of it.

The dates and the first-network-hall condition are in the article, but it describes the rent start as a projection, not a certainty as the claim states.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of the publisher (https://www.theenergymag.com/news/market-news/cleanspark-senior-note-georgia-ai-data-center) in full (4,497 characters, retrieved September 21, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark Names Meta as Tenant Behind $6.6 Billion Data Center Lease - TheEnergyMag

Quote: “The financing presentation projects rent beginning Nov. 30, 2027, after completion of the first network hall, with construction expected to finish in March 2028”

View cached copy (2026-09-21)Live source ↗