Sandersville construction timeline
Company: CleanSpark - Project: Sandersville
The claim, verbatim
Sandersville buildout to commence rent in November 2027 with full buildout completion in March 2028
Source (primary)
CleanSpark reveals Meta as the tenant behind $6.6B Sandersville lease - Yahoo Finance (-, news_article)
View cached copy (2026-09-21)Live source ↗
Quote: “projecting to spend $2.08 billion on the build, which Clean Spark projects will commence rent in November 2027 with the full build out in March 2028”
How we checked this
Checked on September 26, 2026. The cited source supports every part of this claim.
The source says CleanSpark projects rent commencement in November 2027 and full buildout in March 2028.
Confirmed in the source:
- CleanSpark projects rent at Sandersville to commence in November 2027
- CleanSpark projects full buildout at Sandersville in March 2028
What we did: Read our cached copy of the publisher (https://finance.yahoo.com/video/cleanspark-reveals-meta-tenant-behind-232514561.html) in full (15,794 characters, retrieved September 21, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms CleanSpark reveals Meta as the tenant behind $6.6B Sandersville lease - Yahoo Finance
Quote: “projecting to spend $2.08 billion on the build, which Clean Spark projects will commence rent in November 2027 with the full build out in March 2028”