jain.com

Sandersville development costs $11.9 million per MW

Company: CleanSpark - Project: Sandersville

Subject kind
facility capacity
Statement date
2026-09-17
Promised amount
11900000.0 USD/MW
Current status
stated

The claim, verbatim

Development costs at the Sandersville facility are approximately $11.9 million per megawatt of critical IT capacity

Source (primary)

CleanSpark Names Meta as Tenant Behind $6.6 Billion Data Center Lease - TheEnergyMag (-, news_article)
View cached copy (2026-09-21)Live source ↗

Quote: “development costs of approximately $11.9 million per megawatt of critical IT capacity”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms CleanSpark Names Meta as Tenant Behind $6.6 Billion Data Center Lease - TheEnergyMag

Quote: “development costs of approximately $11.9 million per megawatt of critical IT capacity”

View cached copy (2026-09-21)Live source ↗