Total data center portfolio power capacity
Company: Riot
The claim, verbatim
Riot's data center portfolio includes 1,700 MW of fully approved power capacity
Source (primary)
riot 8-K exhibit (riot-20260116xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-21)Live source ↗
Quote: “Data center portfolio of 1.7 GW of fully approved power capacity in one of the leading data center markets in the U.S.”
How we checked this
Checked on September 25, 2026. The cited source supports every part of this claim.
The release describes a data center portfolio of 1.7 GW of fully approved power capacity, which equals 1,700 MW.
Confirmed in the source:
- Riot's data center portfolio has 1.7 GW (1,700 MW) of fully approved power capacity
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1167419/000110465926004551/riot-20260116xex99d1.htm) in full (14,649 characters, retrieved September 21, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms riot 8-K exhibit (riot-20260116xex99d1.htm)
Quote: “Data center portfolio of 1.7 GW of fully approved power capacity in one of the leading data center markets in the U.S.”