Sandersville data center first network hall rent generation

Company: CleanSpark - Project: Sandersville

Subject kind
facility timeline
Statement date
2026-09-17
Promised by
2027-11-30
Current status
stated

The claim, verbatim

The first network hall at Sandersville is expected to begin generating rent on November 30, 2027

Source (primary)

CleanSpark Reveals Meta Behind $6.6 Billion AI Lease, Requires $2.23 Billion Financing - the deep dive (-, news_article)
View cached copy (2026-09-20)Live source ↗

Quote: “Initial rent commencement is targeted for the fourth quarter of 2027, with the first network hall expected to begin generating rent on November 30, 2027”

How we checked this

Checked on September 25, 2026. The cited source supports every part of this claim.

The article gives November 30, 2027 as the expected rent start date for the first network hall.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://thedeepdive.ca/cleanspark-reveals-meta-behind-6-6-billion-ai-lease-requires-2-23-billion-financing/) in full (9,051 characters, retrieved September 20, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark Reveals Meta Behind $6.6 Billion AI Lease, Requires $2.23 Billion Financing - the deep dive

Quote: “Initial rent commencement is targeted for the fourth quarter of 2027, with the first network hall expected to begin generating rent on November 30, 2027”