Sandersville data center construction completion
Company: CleanSpark - Project: Sandersville
The claim, verbatim
Proceeds from the financing will be used to complete construction of the Sandersville data center
Source (primary)
CleanSpark (CLSK) Stock Jumps as Company Plans Over $2B Offering for Data Center Buildout - CoinGape (-, news_article)
View cached copy (2026-09-20)Live source ↗
Quote: “The proceeds will primarily be used to finish construction of the Sandersville Facility”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The article says the proceeds will primarily be used to finish construction of the Sandersville Facility. It adds that some money will also repay prior equity investments and fund debt service reserves.
Confirmed in the source:
- Proceeds from CleanSpark's $2.227 billion senior secured notes offering will be used to finish construction of the Sandersville data center
What we did: Read our cached copy of the publisher (https://coingape.com/cleanspark-clsk-stock-jumps-as-company-plans-over-2b-offering-for-data-center-buildout/) in full (12,602 characters, retrieved September 20, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms CleanSpark (CLSK) Stock Jumps as Company Plans Over $2B Offering for Data Center Buildout - CoinGape
Quote: “The proceeds will primarily be used to finish construction of the Sandersville Facility”
confirms Meta signs 20-year AI data center lease with CleanSpark (NASDAQ: CLSK) as it lines up new debt financing - Stock Titan
Quote: “construction completion expected around March 2028”
confirms CleanSpark plans $2.2B bond offering to fund da... - Pluang
Quote: “The proceeds will finance the completion of the Sandersville data center, reimburse prior equity contributions, and fund debt service reserves.”