jain.com

Sandersville data center capacity

Company: CleanSpark - Project: Sandersville

Subject kind
facility capacity
Statement date
2026-09-17
Promised amount
175.0 MW
Current status
stated

The claim, verbatim

Sandersville Facility is a planned 175 MW critical IT AI data center campus

Source (primary)

Meta signs 20-year AI data center lease with CleanSpark (NASDAQ: CLSK) as it lines up new debt financing - Stock Titan (-, news_article)
View cached copy (2026-09-20)Live source ↗

Quote: “a planned 175 MW critical IT AI data center campus”

How we checked this

Checked on September 25, 2026. The cited source supports every part of this claim.

The presentation describes Sandersville as a 175 MW critical IT AI data center campus that is being developed.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.stocktitan.net/sec-filings/CLSK/8-k-cleanspark-inc-reports-material-event-4948cb8b11c1.html) in full (38,309 characters, retrieved September 20, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Meta signs 20-year AI data center lease with CleanSpark (NASDAQ: CLSK) as it lines up new debt financing - Stock Titan

Quote: “a planned 175 MW critical IT AI data center campus”

View cached copy (2026-09-20)Live source ↗