jain.com

Corsicana Facility planned capacity

Company: Riot - Project: Corsicana

Subject kind
facility capacity
Statement date
2023-03-01
Promised amount
1.0 GW
Current status
stated

The claim, verbatim

Corsicana Facility expected to have approximately one gigawatt of capacity upon completion

Source (primary)

Riot 10-K filed 2023-03-02 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “we are developing a second large-scale Bitcoin mining and data center facility outside of Corsicana, Texas (the "Corsicana Facility"), which, upon completion, is expected to have approximately one gigawatt of capacity available for our own Bitcoin mining and data center hosting services for institutional-scale hosted clients”

How we checked this

Checked on September 21, 2026. The cited source supports every part of this claim.

The document states the Corsicana Facility, upon completion, is expected to have approximately one gigawatt of capacity.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1167419/000155837023002704/riot-20221231x10k.htm) in full (577,023 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot 10-K filed 2023-03-02

Quote: “we are developing a second large-scale Bitcoin mining and data center facility outside of Corsicana, Texas (the "Corsicana Facility"), which, upon completion, is expected to have approximately one gigawatt of capacity available for our own Bitcoin mining and data center hosting services for institutional-scale hosted clients”

View cached copy (2026-09-13)Live source ↗