Ellendale, ND facility energization start
Company: Applied Digital - Project: Ellendale
The claim, verbatim
Began energizing Ellendale facility on March 4, 2023
Source (primary)
Applied Digital 424B3 filed 2023-05-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “The Company took possession of the land on August 15, 2022, built a hosting facility, and began energizing the site on March 4, 2023.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Applied Digital 424B3 filed 2023-05-16
Quote: “The Company took possession of the land on August 15, 2022, built a hosting facility, and began energizing the site on March 4, 2023.”
Record of changes
September 13, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 14, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.