Ellendale North Dakota facility energization March 2023
Company: Applied Digital - Project: Ellendale
The claim, verbatim
Ellendale, North Dakota facility began energizing on March 4, 2023 and will bring total hosting capacity across North Dakota facilities to 280 MW, all contracted to customers
Source (primary)
Applied Digital 424B3 filed 2023-05-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “The Company took possession of the land on August 15, 2022, built a hosting facility, and began energizing the site on March 4, 2023. Once fully energized, this location will bring the Company to 280 MW of total hosting capacity across its facilities in North Dakota, all of which are contracted out to customers on multi-year terms.”
How we checked this
Checked on September 21, 2026. The cited source supports every part of this claim.
The document states the March 4, 2023 energization, the 280 MW North Dakota total, and that all capacity is contracted on multi-year terms.
Confirmed in the source:
- The Ellendale, North Dakota facility began energizing on March 4, 2023
- Once fully energized it brings Applied Digital to 280 MW of total hosting capacity across its North Dakota facilities
- All North Dakota capacity is contracted to customers on multi-year terms
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487923000134/apld-424b3finalprospectus0.htm) in full (53,370 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital 424B3 filed 2023-05-16
Quote: “The Company took possession of the land on August 15, 2022, built a hosting facility, and began energizing the site on March 4, 2023. Once fully energized, this location will bring the Company to 280 MW of total hosting capacity across its facilities in North Dakota, all of which are contracted out to customers on multi-year terms.”