jain.com

Corsicana Facility planned power capacity

Company: Riot - Project: Corsicana

Subject kind
facility capacity
Statement date
2023-08-08
Promised amount
1.0 GW
Current status
stated

The claim, verbatim

Second large-scale Bitcoin mining facility under development outside Corsicana, Texas, expected to have approximately one gigawatt of capacity upon completion

Source (primary)

Riot 424B5 filed 2023-08-09 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “Additionally, we are developing a second large-scale Bitcoin mining and data center facility located outside of Corsicana, Texas (the "Corsicana Facility"), which, upon completion, is expected to have approximately one gigawatt of capacity available for our own Bitcoin mining and data center hosting services for institutional-scale hosted clients.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Riot 424B5 filed 2023-08-09

Quote: “Additionally, we are developing a second large-scale Bitcoin mining and data center facility located outside of Corsicana, Texas (the "Corsicana Facility"), which, upon completion, is expected to have approximately one gigawatt of capacity available for our own Bitcoin mining and data center hosting services for institutional-scale hosted clients.”

View cached copy (2026-09-13)Live source ↗