jain.com

Corsicana Facility total capacity

Company: Riot - Project: Corsicana

Subject kind
facility capacity
Statement date
2024-02-22
Promised amount
1000.0 MW
Current status
stated

The claim, verbatim

Upon completion, Corsicana Facility expected to have approximately one gigawatt of developed capacity

Source (primary)

Riot 10-K filed 2024-02-23 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “Once complete, we expect the Corsicana Facility to have one gigawatt of developed capacity for Bitcoin Mining and Data Center Hosting operations.”

How we checked this

Checked on September 21, 2026. The cited source supports every part of this claim.

The document states the Corsicana Facility is expected to have one gigawatt of developed capacity upon completion.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1167419/000155837024001550/riot-20231231x10k.htm) in full (443,676 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot 10-K filed 2024-02-23

Quote: “Once complete, we expect the Corsicana Facility to have one gigawatt of developed capacity for Bitcoin Mining and Data Center Hosting operations.”

View cached copy (2026-09-13)Live source ↗