jain.com

Corsicana Facility initial phase immersion-cooled capacity

Company: Riot - Project: Corsicana

Subject kind
facility capacity
Statement date
2024-02-22
Promised amount
400.0 MW
Current status
stated

The claim, verbatim

The initial phase of the development of the Corsicana Facility involves the construction of 400 megawatts of immersion-cooled Bitcoin Mining and Data Center Hosting infrastructure

Source (primary)

Riot 10-K filed 2024-02-23 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “The initial phase of the development of the Corsicana Facility involves the construction of 400 megawatts ("MW") of immersion-cooled Bitcoin Mining and Data Center Hosting infrastructure”

How we checked this

Checked on September 21, 2026. The cited source supports every part of this claim.

The document states this verbatim.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1167419/000155837024001550/riot-20231231x10k.htm) in full (443,676 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot 10-K filed 2024-02-23

Quote: “The initial phase of the development of the Corsicana Facility involves the construction of 400 megawatts ("MW") of immersion-cooled Bitcoin Mining and Data Center Hosting infrastructure”

View cached copy (2026-09-13)Live source ↗