Follow-on purchase order from MicroBT for additional miners
Company: Riot - Project: Corsicana
What the later record shows
The date slipped · new target June 30, 2026
The follow-on miners were promised for deployment through mid-2024. Filings repeatedly moved full receipt of the 2023 purchase orders, most recently to Q2 2026.
“all miners under these purchase orders are expected to be received and deployed by mid-2025.”
2025-02-27 · Riot 10-K filed 2025-02-28 View cached copy (2026-08-31)Live source ↗
“all miners under these purchase orders are expected to be received by the second quarter of 2026, with deployment following on an ongoing basis”
2025-10-29 · Riot 10-Q filed 2025-10-30 View cached copy (2026-08-31)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Executed follow-on purchase order on December 4, 2023 to acquire 66,560 additional MicroBT miners expected to be delivered to Corsicana and deployed through mid-2024
Source (primary)
Riot 424B5 filed 2024-02-26 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “Subsequently, on December 4, 2023, we executed a follow-on purchase order, pursuant to our purchase option under the Master Agreement, to acquire an additional 66,560 miners from MicroBT, which are expected to be delivered to our Corsicana location and deployed through mid-2024.”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The document states the December 4, 2023 follow-on order for 66,560 MicroBT miners, delivered to Corsicana and deployed through mid-2024.
Confirmed in the source:
- Riot executed a follow-on purchase order on December 4, 2023
- The order was to acquire an additional 66,560 MicroBT miners
- The miners were expected to be delivered to the Corsicana location
- The miners were expected to be deployed through mid-2024
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1167419/000155837024001713/tmb-20240226x424b5.htm) in full (142,665 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Riot 424B5 filed 2024-02-26
Quote: “Subsequently, on December 4, 2023, we executed a follow-on purchase order, pursuant to our purchase option under the Master Agreement, to acquire an additional 66,560 miners from MicroBT, which are expected to be delivered to our Corsicana location and deployed through mid-2024.”
delays Riot 10-K filed 2025-02-28
Quote: “all miners under these purchase orders are expected to be received and deployed by mid-2025.”
delays Riot 10-Q filed 2025-10-30
Quote: “all miners under these purchase orders are expected to be received by the second quarter of 2026, with deployment following on an ongoing basis”