Corsicana Facility expected capacity upon completion
Company: Riot - Project: Corsicana
The claim, verbatim
The Corsicana Facility, upon completion, is expected to have approximately one gigawatt (1,000 megawatts) of Bitcoin mining capacity
Source (primary)
Riot DEF 14A filed 2024-04-29 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “Additionally, we have made significant strides in developing our second large-scale Bitcoin mining facility outside of Corsicana, Texas (the "Corsicana Facility") which, upon completion, is expected to have approximately one gigawatt (1,000 megawatts ("MW")) of Bitcoin mining capacity.”
How we checked this
Additional evidence
confirms Riot DEF 14A filed 2024-04-29
Quote: “Additionally, we have made significant strides in developing our second large-scale Bitcoin mining facility outside of Corsicana, Texas (the "Corsicana Facility") which, upon completion, is expected to have approximately one gigawatt (1,000 megawatts ("MW")) of Bitcoin mining capacity.”