Hunt utility partner engagement
Company: Core Scientific - Project: Hunt County
The claim, verbatim
Core Scientific has a utility partner for the Hunt, Texas interconnection project
Source (primary)
Core Scientific 8-K filed 2026-09-10 (SEC EDGAR, sec_filing)
View cached copy (2026-09-11)Live source ↗
Quote: “The Company and its utility partner have completed the required interconnection studies, received ERCOT approval of its 431 Megawatt stability study, posted the required financial collateral, has ordered long-lead equipment, commenced construction”
How we checked this
Checked on September 20, 2026. The cited source supports every part of this claim.
The document refers to 'The Company and its utility partner' completing interconnection work for the Hunt site.
Confirmed in the source:
- Core Scientific has a utility partner involved in the Hunt, Texas interconnection project
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1839341/000183934126000023/core-20260910.htm) in full (5,482 characters, retrieved September 11, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Core Scientific 8-K filed 2026-09-10
Quote: “The Company and its utility partner have completed the required interconnection studies, received ERCOT approval of its 431 Megawatt stability study, posted the required financial collateral, has ordered long-lead equipment, commenced construction”