Where it stands
Nebius is leasing capacity at a Mega Or data center in Masmiya, Israel, which is still described as planned. An earlier 2026 agreement covered 22MW at Masmiya. A November 2026 agreement adds 134MW split across Masmiya and Beit Shemesh, but the passages do not say how much of that goes to Masmiya, so planned_mw shows only the stated 22MW.
22 MW planned
| Phase | MW | Status | Date | Source |
|---|---|---|---|---|
| Second Mega Or agreement - Masmiya | 22 | planned | a second agreement for 58MW and 22MW of capacity at the Beit Shemesh and Masmiya data centers, respectively, was signed. 2026-11-20 View cached copy (2026-11-21)Live source ↗Archive.org ↗ | |
| Third Mega Or agreement - expansion (shared with Beit Shemesh) | planned | 2026-11-20 | the neocloud has signed on to take more capacity across two data centers: one under construction in Beit Shemesh, and another planned in Masmiya. 2026-11-20 View cached copy (2026-11-21)Live source ↗Archive.org ↗ |
Assessed November 22, 2026 from the newest filings, releases and reporting that name this project (newest relied on: November 20, 2026).
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
Claims about this project
Site intelligence
How we located this site
- Starting point (the project's stated locality) 2026-11-23
Masmiya, Israel → 31.77927, 34.76936 (locality) - No site-level evidence yet 2026-11-23
no address, road, landmark or coordinates tie this project to a specific parcel yet -- the town is shown, NOT the site - OpenStreetMap features nearby 2026-11-23
0 named match(es)