jain.com

Abu Dhabi

Project of Marathon Digital

Kind
mining
Location
Abu Dhabi, United Arab Emirates
State/region
Abu Dhabi
Country
UAE
Status
announced

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today--
Contracted a customer is on the hook--
Under construction--
Permitted--
Interconnect approved utility has agreed to deliver--
Interconnect requested in a queue, nothing approved--
Announced a press-release figure250 MW2023-03-15Abu Dhabi mining facility capacity

Who has claimed this site

Capacity commitments in the order they were announced. A commitment that ended shows why.

2023-03-15
FS Innovation - jv partner source

Claims about this project

2023-03-15 - stated
2023-03-15 - stated
2023-03-15 - stated
2023-03-15 - stated
2023-03-15 - delayed
Abu Dhabi mining JV formation with capital commitment 81200.0 thousand USD. Promised by 2023-12-31.
2023-03-15 - delayed
2023-03-15 - delayed
FS Innovation Abu Dhabi digital asset mining joint venture 406000.0 USD_thousands. Promised by 2023-12-31.
2023-03-15 - delayed
Abu Dhabi mining facility operational timeline 250.0 MW. Promised by 2023-12-31.
2023-03-15 - delayed
2023-03-15 - delayed
2023-03-15 - delayed
Abu Dhabi joint venture capital contributions 81200000.0 USD. Promised by 2023-12-31.
2023-03-15 - stated
2023-03-15 - stated
2023-03-15 - stated
2023-03-15 - delayed
2023-03-15 - stated
2023-03-15 - stated