Abu Dhabi mining facility initial capacity
Company: Marathon Digital - Project: Abu Dhabi
The claim, verbatim
Initial Abu Dhabi project will consist of two digital asset mining sites comprising 250 MW in immersion cooling
Source (primary)
Marathon Digital 10-K filed 2023-03-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “The initial project by the ADGM Entity shall consist of two digital asset mining sites comprising 250 MW in Abu Dhabi”
How we checked this
Checked on September 21, 2026. The cited source supports every part of this claim.
The document states the two sites total 250 MW and, in the Operations section, specifies '250 MW in immersion in Abu Dhabi.'
Confirmed in the source:
- The initial Abu Dhabi project consists of two digital asset mining sites comprising 250 MW
- The 250 MW will use immersion cooling
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1507605/000149315223007879/form10-k.htm) in full (445,884 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Marathon Digital 10-K filed 2023-03-16
Quote: “The initial project by the ADGM Entity shall consist of two digital asset mining sites comprising 250 MW in Abu Dhabi”