Abu Dhabi mining facility initial capacity

Company: Marathon Digital - Project: Abu Dhabi

Subject kind
facility capacity
Statement date
2023-03-15
Promised amount
250.0 MW
Current status
stated

The claim, verbatim

Initial Abu Dhabi project will consist of two digital asset mining sites comprising 250 MW in immersion cooling

Source (primary)

Marathon Digital 10-K filed 2023-03-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “The initial project by the ADGM Entity shall consist of two digital asset mining sites comprising 250 MW in Abu Dhabi”

How we checked this

Checked on September 21, 2026. The cited source supports every part of this claim.

The document states the two sites total 250 MW and, in the Operations section, specifies '250 MW in immersion in Abu Dhabi.'

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1507605/000149315223007879/form10-k.htm) in full (445,884 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Marathon Digital 10-K filed 2023-03-16

Quote: “The initial project by the ADGM Entity shall consist of two digital asset mining sites comprising 250 MW in Abu Dhabi”

View cached copy (2026-09-13)Live source ↗