Kiowa
Project of IREN
Where it stands
IREN's Kiowa, Oklahoma campus is listed with 1,600MW of planned gross power capacity as of June 30, 2026. The most recent filing (Oct 2026) describes Kiowa as being in development, with data center capacity expected to ramp from 2028. No passage reports construction or energized capacity at Kiowa.
1,600 MW planned
| Phase | MW | Status | Date | Source |
|---|---|---|---|---|
| Kiowa campus | 1600 | planned | Sweetwater 2 (Texas, USA) 600 Kiowa (Oklahoma, USA) 1,600 Badajoz, Extremadura, Spain 300 2026-08-26 View cached copy (2026-08-30)Live source ↗ |
Assessed October 18, 2026 from the newest filings, releases and reporting that name this project (newest relied on: October 12, 2026).
Claims about this project
2026-05-07 - stated
2028+ Expansion - Sweetwater and Kiowa. Promised by 2028-01-01.
2026-08-18 - stated