Deadlines
Every open claim that carries a date the company promised something by, soonest first. Dates already past stay listed as "outcome unconfirmed" until a later filing or release shows what happened; that is not a finding that the date was missed. A claim moves to Delayed only when a later source shows it slipped.
3,815 total · showing 3,001–3,100
- Cipher Mining - Colchis interconnection facility energization stated · promised 2028-12-31 · stated 2025-11-03
- Core Scientific - AMD full 530 MW delivery stated · promised 2028-12-31 · stated 2026-07-28
- Cipher Mining - Colchis energization target stated · promised 2028-12-31 · stated 2026-02-23
- TeraWulf - Muskie first 500 MW phase ramp in 2028 stated · promised 2028-12-31 · stated 2026-10-10
- Core Scientific - Full portfolio dedicated to AI colocation by end of 2028 stated · promised 2028-12-31 · stated 2026-03-02
- CoreWeave - Indonesia facilities online stated · promised 2028-12-31 · stated 2026-08-01
- CoreWeave - Three Indonesia facilities (360 MW) online in 2028 stated · promised 2028-12-31 · stated 2026-10-07
- TeraWulf - Cayuga Phase II +162 MW in 2028 stated · promised 2028-12-31 · stated 2025-09-04
- TeraWulf - Muskie first 500 MW phase ramp in 2028 stated · promised 2028-12-31 · stated 2026-10-09
- Applied Digital - ~2 GW operating capacity by end of 2028 stated · promised 2028-12-31 · stated 2026-10-08
- TeraWulf - Zero-carbon energy target stated · promised 2028-12-31 · stated 2023-01-31
- Applied Digital - Data center capacity delivery completion stated · promised 2028-12-31 · stated 2026-08-28
- Applied Digital - Total AI data center capacity stated · promised 2028-12-31 · stated 2026-09-01
- CoreWeave - Indonesia data centers add 360 MW stated · promised 2028-12-31 · stated 2026-10-01
- Core Scientific - Multi-campus deployment completion timeline stated · promised 2028-12-31 · stated 2026-07-28
- Applied Digital - Minimum lease payments fiscal 2028 stated · promised 2028-12-31 · stated 2026-09-09
- TeraWulf - Fluidstack JV options 336 MW stated · promised 2028-12-31 · stated 2025-11-10
- Applied Digital - All campus deliveries completion stated · promised 2028-12-31 · stated 2026-09-07
- TeraWulf - Zero-Carbon Energy Target by 2028 stated · promised 2028-12-31 · stated 2022-06-12
- TeraWulf - Zero-carbon energy consumption target by 2028 stated · promised 2028-12-31 · stated 2022-04-25
- TeraWulf - Abernathy Phase II buildout stated · promised 2028-12-31 · stated 2025-10-27
- Applied Digital - Annual lease revenue upon full campus delivery stated · promised 2028-12-31 · stated 2026-09-07
- Applied Digital - Polaris Forge 3 delivery stated · promised 2028-12-31 · stated 2026-10-06
- Applied Digital - Polaris Forge 3 contracted capacity and revenue stated · promised 2028-12-31 · stated 2026-07-28
- Cipher Mining - Colchis AEP interconnection agreement targeting energization stated · promised 2028-12-31 · stated 2026-02-23
- Applied Digital - Minimum lease payments for fiscal 2028 stated · promised 2028-12-31 · stated 2026-09-09
- Applied Digital - Total contracted critical IT capacity stated · promised 2028-12-31 · stated 2026-09-25
- Hut 8 - Texas facility expected operating income in 2028 stated · promised 2028-12-31 · stated 2026-09-01
- TeraWulf - Muskie first 500 MW phase ramp targeted 2028 stated · promised 2028-12-31 · stated 2026-10-04
- Applied Digital - ~2 GW capacity by end of 2028 stated · promised 2028-12-31 · stated 2026-10-07
- TeraWulf - Fluidstack JV options 336 MW stated · promised 2028-12-31 · stated 2025-11-10
- TeraWulf - Muskie campus 500 MW capacity by H2 2028 stated · promised 2028-12-31 · stated 2026-08-21
- Applied Digital - Finland campus initial power availability targeted for 2028 stated · promised 2028-12-31 · stated 2026-10-14
- TeraWulf - Muskie phase 1 (500 MW) on track for H2 2028 stated · promised 2028-12-31 · stated 2026-10-05
- Applied Digital - Finland initial power availability in 2028 stated · promised 2028-12-31 · stated 2026-10-08
- Applied Digital - 1.51 GW delivered by 2028 stated · promised 2028-12-31 · stated 2026-10-08
- Applied Digital - PF2, PF3, DF1, DF2 delivery through 2028 stated · promised 2028-12-31 · stated 2026-09-25
- Core Scientific - AMD 530 MW full delivery completion stated · promised 2028-12-31 · stated 2026-07-28
- Applied Digital - Polaris Forge 3 hyperscaler leases 300 MW stated · promised 2028-12-31 · stated 2026-07-29
- Applied Digital - AI data center power capacity target stated · promised 2028-12-31 · stated 2026-09-21
- Applied Digital - Contracted capacity planned for delivery by 2028 stated · promised 2028-12-31 · stated 2026-08-20
- Cipher Mining - Colchis 1000 MW facility 2028 energization target stated · promised 2028-12-31 · stated 2026-02-23
- TeraWulf - Muskie Phase I Capacity stated · promised 2028-12-31 · stated 2026-08-04
- Applied Digital - High-grade hyperscaler Polaris Forge 3 lease stated · promised 2028-12-31 · stated 2026-09-25
- TeraWulf - Cayuga Phase II 300 MW total in 2028 stated · promised 2028-12-31 · stated 2025-08-14
- Applied Digital - Finland campus initial power in 2028 stated · promised 2028-12-31 · stated 2026-10-07
- Applied Digital - Finland initial power availability from 2028 stated · promised 2028-12-31 · stated 2026-10-13
- Applied Digital - Polaris Forge 3 delivery stated · promised 2028-12-31 · stated 2026-10-03
- TeraWulf - Muskie first 500 MW phase ramp in 2028 stated · promised 2028-12-31 · stated 2026-10-08
- TeraWulf - 100% zero-carbon energy target by 2028 stated · promised 2028-12-31 · stated 2023-03-30
- Applied Digital - Roughly 2 GW by end of 2028 stated · promised 2028-12-31 · stated 2026-10-11
- TeraWulf - Cayuga Phase 2 stated · promised 2028-12-31 · stated 2025-08-14
- CoreWeave - Three Indonesia facilities with 360 MW IT power in Greater Jakarta stated · promised 2028-12-31 · stated 2026-08-06
- Applied Digital - Data center delivery timeline through 2028 stated · promised 2028-12-31 · stated 2026-09-07
- Applied Digital - 1,410 MW capacity backlog by 2028 stated · promised 2028-12-31 · stated 2026-09-01
- TeraWulf - 100% zero-carbon energy target by 2028 stated · promised 2028-12-31 · stated 2022-03-30
- TeraWulf - Zero-carbon energy consumption target stated · promised 2028-12-31 · stated 2022-03-30
- Applied Digital - Finland project first power delivery stated · promised 2028-12-31 · stated 2026-10-08
- TeraWulf - Muskie first phase ramp expected 2028 stated · promised 2028-12-31 · stated 2026-10-08
- Applied Digital - Finland power capacity agreement stated · promised 2028-12-31 · stated 2026-10-08
- Core Scientific - 2028 AI colocation dedication target stated · promised 2028-12-31 · stated 2026-03-02
- Cipher Mining - 1 GW FTM site energization stated · promised 2028-12-31 · stated 2026-10-12
- TeraWulf - Muskie first 500 MW phase to begin ramping in 2028 stated · promised 2028-12-31 · stated 2026-10-12
- TeraWulf - Muskie Data Phase I ramp stated · promised 2028-12-31 · stated 2026-08-04
- Applied Digital - 1.3 GW marketed capacity mostly energizing in 2028 stated · promised 2028-12-31 · stated 2026-10-08
- Applied Digital - Finland AI Factory campus, up to 1 GW, initial power from 2028 stated · promised 2028-12-31 · stated 2026-10-07
- TeraWulf - Exclusive Fluidstack JV options for future capacity stated · promised 2028-12-31 · stated 2025-11-10
- Applied Digital - Minimum contracted lease payments in fiscal 2028 stated · promised 2028-12-31 · stated 2026-09-07
- TeraWulf - Zero-carbon energy consumption target stated · promised 2028-12-31 · stated 2022-04-12
- Core Scientific - AMD AI compute capacity expansion opportunity stated · promised 2028-12-31 · stated 2026-07-27
- TeraWulf - Muskie first phase initial ramp targeted for 2028 stated · promised 2028-12-31 · stated 2026-10-17
- Applied Digital - Finland agreement for up to 1 GW, initial availability 2028 stated · promised 2028-12-31 · stated 2026-10-08
- Applied Digital - Expected capacity by 2028 stated · promised 2028-12-31 · stated 2026-09-01
- Applied Digital - 430 MW capacity by 2028 stated · promised 2028-12-31 · stated 2026-09-21
- Applied Digital - Finland campus initial power availability targeted for 2028 stated · promised 2028-12-31 · stated 2026-10-06
- CoreWeave - Share of CoreWeave RPO scheduled through 2028 stated · promised 2028-12-31 · stated 2026-10-16
- Core Scientific - AMD 530 MW fully delivered by end of 2028 stated · promised 2028-12-31 · stated 2026-07-28
- Core Scientific - AMD/neocloud 530 MW full delivery by end of 2028 stated · promised 2028-12-31 · stated 2026-10-14
- IREN - Bundey campus energization timing stated · promised 2028-12-31 · stated 2026-10-14
- Applied Digital - 1.51 GW critical IT load by 2028 stated · promised 2028-12-31 · stated 2026-09-29
- Core Scientific - Multi-campus deployments through 2028 stated · promised 2028-12-31 · stated 2026-07-28
- Applied Digital - Finland project initial power availability in 2028 stated · promised 2028-12-31 · stated 2026-10-17
- Applied Digital - Backlog capacity by 2028 stated · promised 2028-12-31 · stated 2026-09-01
- Applied Digital - Finland project first power targeted 2028 stated · promised 2028-12-31 · stated 2026-10-08
- Applied Digital - Finland site first 100 MW in 2028 stated · promised 2028-12-31 · stated 2026-10-08
- TeraWulf - Muskie Phase I 500 MW ramp Q4 2028 stated · promised 2028-12-31 · stated 2026-08-04
- Cipher Mining - Apollo site target energization stated · promised 2028-12-31 · stated 2026-10-12
- TeraWulf - Cayuga Phase II expansion stated · promised 2028-12-31 · stated 2025-09-04
- Applied Digital - Polaris Forge 3 delivery dates stated · promised 2028-12-31 · stated 2026-09-29
- CoreWeave - Three Indonesia data centers online in 2028 stated · promised 2028-12-31 · stated 2026-10-01
- CoreWeave - Three Indonesia data centers (360 MW) online in 2028 stated · promised 2028-12-31 · stated 2026-10-01
- Applied Digital - Base Electron gas-fired power generation partnership stated · promised 2029-01-01 · stated 2026-09-17
- TeraWulf - $100M TeraWulf-funded residential bill credits, pending PSC approval stated · promised 2029-01-01 · stated 2026-10-05
- Applied Digital - Base Electron capacity delivery timeline stated · promised 2029-01-01 · stated 2026-09-04
- TeraWulf - TeraWulf-funded $100M residential bill credits for Kentucky Power customers stated · promised 2029-01-01 · stated 2026-10-07
- Applied Digital - Base Electron gas-fired generation capacity 2029-2030 stated · promised 2029-01-01 · stated 2026-09-17
- TeraWulf - $100M residential bill credits funded by TeraWulf stated · promised 2029-01-01 · stated 2026-10-05
- TeraWulf - Kentucky Power amended agreement: $100M bill credits funded by TeraWulf stated · promised 2029-01-01 · stated 2026-10-05
- TeraWulf - TeraWulf funds $100M residential bill credits for Kentucky Power customers stated · promised 2029-01-01 · stated 2026-10-05
- Applied Digital - Base Electron power capacity arrival in 2029 stated · promised 2029-01-01 · stated 2026-09-03