Deadlines
Every open claim that carries a date the company promised something by, soonest first. Dates already past stay listed as "outcome unconfirmed" until a later filing or release shows what happened; that is not a finding that the date was missed. A claim moves to Delayed only when a later source shows it slipped.
3,815 total · showing 2,501–2,600
- Riot - Rockdale initial 96 MW delivery December 2027 stated · promised 2027-12-31 · stated 2026-09-28
- Nebius - Deliberately limiting commitments to 2027 GPU capacity sales stated · promised 2027-12-31 · stated 2026-09-11
- IREN - 300MW data center at Sweetwater 1 targeting Q4 2027 delivery stated · promised 2027-12-31 · stated 2026-09-08
- CoreWeave - $10.6B debt due by end of 2027 stated · promised 2027-12-31 · stated 2026-10-18
- Cipher Mining - Power access cost commitment through 2027 stated · promised 2027-12-31 · stated 2023-03-13
- Core Scientific - 1.3 GW+ billable capacity by 2027 stated · promised 2027-12-31 · stated 2025-05-06
- Cipher Mining - Power supply agreement pricing through 2027 stated · promised 2027-12-31 · stated 2023-03-13
- Riot - First phase Rockdale capacity delivery stated · promised 2027-12-31 · stated 2026-08-24
- Hut 8 - Data center projects in Louisiana and Texas coming online stated · promised 2027-12-31 · stated 2026-08-15
- CoreWeave - Projection of 3.2 GW capacity by end of 2027 stated · promised 2027-12-31 · stated 2026-08-25
- Core Scientific - Pathway to 1.3 GW+ billable power by 2027 stated · promised 2027-12-31 · stated 2025-05-07
- Core Scientific - $500M+ annual run-rate cost savings by end of 2027 stated · promised 2027-12-31 · stated 2025-10-13
- Core Scientific - Critical IT Load capacity target by 2027 stated · promised 2027-12-31 · stated 2025-02-26
- Applied Digital - Polaris Forge 1 third 150 MW building stated · promised 2027-12-31 · stated 2025-10-09
- Hut 8 - Annual NOI over US$1.75B from AI data centre leases stated · promised 2027-12-31 · stated 2026-09-27
- IREN - FY2027 Capital Expenditure stated · promised 2027-12-31 · stated 2026-08-27
- Nebius - 2027 capacity sales visibility stated · promised 2027-12-31 · stated 2026-08-20
- CoreWeave - Debt Maturity - 2027 stated · promised 2027-12-31 · stated 2026-09-01
- CleanSpark - Sandersville data center online date stated · promised 2027-12-31 · stated 2026-09-17
- IREN - Prince George and Mackenzie liquid-cooled deployments in 2027 stated · promised 2027-12-31 · stated 2026-10-12
- Applied Digital - Third 150 MW Polaris Forge 1 facility planned 2027 stated · promised 2027-12-31 · stated 2025-10-09
- Riot - Anthropic lease delivery schedule at Rockdale stated · promised 2027-12-31 · stated 2026-08-10
- Applied Digital - Delta Forge 1 hyperscaler lease stated · promised 2027-12-31 · stated 2026-07-27
- Cipher Mining - Reveille, Mikeska, Milsing, McLennan 2027 growth sites stated · promised 2027-12-31 · stated 2025-05-05
- Applied Digital - Delta Forge 1 capacity stated · promised 2027-12-31 · stated 2026-07-27
- Core Scientific - CoreWeave HPC delivery ~590 MW by 2027 stated · promised 2027-12-31 · stated 2025-02-26
- Nebius - 2027 revenue projection stated · promised 2027-12-31 · stated 2026-09-23
- Cipher Mining - 170 MW powered land for 2026-2027 stated · promised 2027-12-31 · stated 2025-09-24
- WhiteFiber - 100+ MW additional capacity in 2027 stated · promised 2027-12-31 · stated 2026-08-21
- Core Scientific - $500M annual run-rate cost savings by end of 2027 stated · promised 2027-12-31 · stated 2025-07-06
- CleanSpark - Sandersville first data hall targeted Q4 CY2027 stated · promised 2027-12-31 · stated 2026-10-10
- Hut 8 - West Feliciana data center ~200 permanent jobs stated · promised 2027-12-31 · stated 2026-10-06
- CleanSpark - Georgia data center initial data hall delivery stated · promised 2027-12-31 · stated 2026-09-18
- IREN - Sweetwater 2 substation energization stated · promised 2027-12-31 · stated 2025-11-05
- Applied Digital - Real estate project financing for Building A construction stated · promised 2027-12-31 · stated 2025-01-07
- Riot - Anthropic data center initial 96 MW deployment stated · promised 2027-12-31 · stated 2026-08-13
- Nebius - Entire 2027 capacity sellable now stated · promised 2027-12-31 · stated 2026-10-01
- IREN - 2027 capacity expansion stated · promised 2027-12-31 · stated 2026-09-14
- Cipher Mining - Reveille 70 MW facility stated · promised 2027-12-31 · stated 2025-11-02
- Nebius - Management indicates potential to sell much of 2027 GPU capacity stated · promised 2027-12-31 · stated 2026-09-10
- IREN - 2027 Capacity Expansion to 1,210MW stated · promised 2027-12-31 · stated 2026-05-07
- IREN - 1.2GW capacity target 2027 stated · promised 2027-12-31 · stated 2026-08-13
- Riot - Anthropic data center - first phase delivery stated · promised 2027-12-31 · stated 2026-09-16
- IREN - Sweetwater initial megawatt delivery stated · promised 2027-12-31 · stated 2026-09-10
- Nebius - New AI infrastructure capacity planned for 2027 stated · promised 2027-12-31 · stated 2026-09-11
- CleanSpark - Sandersville deliveries begin Q4 2027 stated · promised 2027-12-31 · stated 2026-10-09
- CleanSpark - Sandersville lease deliveries begin Q4 2027 stated · promised 2027-12-31 · stated 2026-07-10
- Core Scientific - Dalton GA site delivery stated · promised 2027-12-31 · stated 2026-07-28
- CoreWeave - Debt maturities through 2027 stated · promised 2027-12-31 · stated 2026-10-18
- Riot - Frontier AI lab 191 MW lease rent commencement Dec 2027 stated · promised 2027-12-31 · stated 2026-09-28
- TeraWulf - Cayuga power access 2027 stated · promised 2027-12-31 · stated 2025-09-04
- CoreWeave - Debt Maturity Schedule for 2027 stated · promised 2027-12-31 · stated 2026-09-01
- IREN - Compute capacity addition in 2027 stated · promised 2027-12-31 · stated 2026-09-14
- Riot - Anthropic first phase deployment (96 MW) stated · promised 2027-12-31 · stated 2026-08-21
- Applied Digital - Polaris Forge 1 third 150 MW building stated · promised 2027-12-31 · stated 2026-01-07
- Riot - 96 MW first phase delivery to frontier AI customer stated · promised 2027-12-31 · stated 2026-08-17
- IREN - 1.2 GW AI Cloud capacity by 2027 stated · promised 2027-12-31 · stated 2026-08-18
- IREN - AI cloud capacity plan for 2027 stated · promised 2027-12-31 · stated 2026-08-20
- Applied Digital - Polaris Forge 1 third data center delivery timeline stated · promised 2027-12-31 · stated 2026-07-28
- Riot - Rockdale initial deployment (96MW) stated · promised 2027-12-31 · stated 2026-08-20
- Hut 8 - River Bend 2027 revenue projection stated · promised 2027-12-31 · stated 2026-04-26
- Nebius - 1+ GW deployment target 2027 stated · promised 2027-12-31 · stated 2026-08-25
- WhiteFiber - 100+ MW capacity expansion target stated · promised 2027-12-31 · stated 2026-08-21
- Nebius - Deploy >1 GW per year from 2027 stated · promised 2027-12-31 · stated 2026-10-13
- Core Scientific - AMD Dalton GA initial delivery stated · promised 2027-12-31 · stated 2026-07-27
- Nebius - 2027 new capacity deployment plan stated · promised 2027-12-31 · stated 2026-08-13
- CoreWeave - 2027 annualized revenue guidance stated · promised 2027-12-31 · stated 2026-09-11
- TeraWulf - Justified Data 2H 2027 delivery stated · promised 2027-12-31 · stated 2026-05-14
- IREN - 1.2 GW capacity target for 2027 stated · promised 2027-12-31 · stated 2026-08-13
- Core Scientific - 1.3 GW+ critical IT load by 2027 stated · promised 2027-12-31 · stated 2025-02-25
- Nebius - 2027 capacity sellable today stated · promised 2027-12-31 · stated 2026-10-01
- Core Scientific - Muskogee Polaris initial power delivery stated · promised 2027-12-31 · stated 2026-05-06
- Riot - December 2027 data center delivery stated · promised 2027-12-31 · stated 2026-09-26
- Riot - Rockdale AI lab first 96 MW rent start stated · promised 2027-12-31 · stated 2026-10-08
- Hut 8 - Beacon Point AI data center operational timeline stated · promised 2027-12-31 · stated 2026-05-06
- Hut 8 - Beacon Point AI data center - 352 MW capacity stated · promised 2027-12-31 · stated 2026-05-06
- Applied Digital - Minimum lease payments for fiscal 2027 stated · promised 2027-12-31 · stated 2026-09-09
- Applied Digital - Delta Forge 1 facility expected to begin operations in 2027 stated · promised 2027-12-31 · stated 2026-09-07
- Core Scientific - Pathway to 1.3 GW+ critical IT load by 2027 stated · promised 2027-12-31 · stated 2025-02-26
- CoreWeave - $500M annual run-rate cost savings by end-2027 stated · promised 2027-12-31 · stated 2025-07-06
- IREN - Iren 500 MW IT load target for 2027 stated · promised 2027-12-31 · stated 2026-08-28
- Riot - Anthropic phase 1 (96 MW) stated · promised 2027-12-31 · stated 2026-10-08
- CoreWeave - 2027 revenue target and contract lock-in stated · promised 2027-12-31 · stated 2026-09-11
- Applied Digital - Polaris Forge 1 third 150 MW building in 2027 stated · promised 2027-12-31 · stated 2026-04-08
- Cipher Mining - Average electricity cost from power agreements stated · promised 2027-12-31 · stated 2023-03-13
- Nebius - 2027 capacity deployment plan stated · promised 2027-12-31 · stated 2026-09-04
- Hut 8 - West Feliciana data center construction completion 2027 stated · promised 2027-12-31 · stated 2026-10-05
- Nebius - Margin improvement from owned data centers in H2 2027 stated · promised 2027-12-31 · stated 2026-10-06
- WhiteFiber - Next site acquisition in 2027 stated · promised 2027-12-31 · stated 2026-08-14
- Applied Digital - Polaris Forge 1 - Third data center under construction stated · promised 2027-12-31 · stated 2026-07-28
- Applied Digital - Third 150MW Ellendale building (option) ready 2027 stated · promised 2027-12-31 · stated 2025-06-01
- WhiteFiber - Two pending North Carolina transactions to unlock over 100 MW stated · promised 2027-12-31 · stated 2026-09-10
- Nebius - Planned capacity addition in 2027 stated · promised 2027-12-31 · stated 2026-09-11
- IREN - Fiscal 2027 Capital Investment Plan stated · promised 2027-12-31 · stated 2026-09-14
- Riot - December 2027 delivery milestone stated · promised 2027-12-31 · stated 2026-09-26
- Nebius - Deploy >1 GW per year from 2027 stated · promised 2027-12-31 · stated 2026-10-13
- Applied Digital - Polaris Forge 2 operational timeline stated · promised 2027-12-31 · stated 2025-09-21
- Nebius - 2027 capacity demand fulfillment stated · promised 2027-12-31 · stated 2026-09-09
- Nebius - New capacity addition in 2027 stated · promised 2027-12-31 · stated 2026-09-11
- Nebius - 1 GW annual deployment in 2027 stated · promised 2027-12-31 · stated 2026-08-14