jain.com

PSC approves 482 MW grid connection

Company: TeraWulf

Subject kind
regulatory
Statement date
2026-08-21
Promised amount
482.0 MW
Current status
stated

The claim, verbatim

PSC approved TeraWulf to use an existing 482-megawatt connection to the grid

Source (primary)

KY utility regulator OKs electricity contract for TeraWulf’s Hancock County data center project - WEKU (-, news_article)
View cached copy (2026-08-31)Live source ↗Archive.org ↗

Quote: “The PSC approved TeraWulf to use an existing 482-megawatt connection to the grid.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms KY utility regulator OKs electricity contract for TeraWulf’s Hancock County data center project - WEKU

Quote: “The PSC approved TeraWulf to use an existing 482-megawatt connection to the grid.”

View cached copy (2026-08-31)Live source ↗Archive.org ↗