Morgantown power generation facility acquisition planned

Company: TeraWulf

This claim was marked delayed on October 9, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
acquisition
Statement date
2026-02-27
Promised by
2026-06-30
Promised amount
210.0 MW
Current status
delayed

What the later record shows

The date slipped · new target December 31, 2026

The Morgantown acquisition had not closed by the end of Q2 2026. FERC authorized it on July 29, 2026, and the company now expects to close in the second half of 2026.

“On July 29, 2026, FERC authorized the pending acquisition of the Morgantown generating station.”
2026-08-04 · TeraWulf 10-Q filed 2026-08-05 View cached copy (2026-08-31)Live source ↗
“Subject to the remaining closing conditions and required approvals, the Company expects to close on the Morgantown acquisition in the second half of 2026.”
2026-08-04 · TeraWulf 10-Q filed 2026-08-05 View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Company entered into Equity and Asset Purchase Agreement for Morgantown generating station in Charles County, Maryland featuring approximately 210 MW of current operational capacity; closing subject to third-party consents and regulatory approvals including from FERC; expected to close in Q2 2026

Source (primary)

View 10-K PDF (IR page (investors.terawulf.com), ir_release)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “Additionally, on February 2, 2026, the Company issued a press release announcing the entry into an Equity and Asset Purchase Agreement (the "Morgantown Purchase Agreement") for the Morgantown generating station in Charles County, Maryland... contemplates the acquisition of the Morgantown generating station, a grid-connected power generation facility with approximately 210 MW of current operational capacity... The Company expects to close on the Morgantown acquisition in the second quarter of 2026, subject to receiving these consents and approvals”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The 10-K describes the Morgantown agreement, the 210 MW capacity, the FERC and other approval conditions, and the expected second-quarter 2026 closing.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://investors.terawulf.com/sec-filings/all-sec-filings/content/0001083301-26-000031/0001083301-26-000031.pdf) in full (556,251 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms View 10-K PDF

Quote: “Additionally, on February 2, 2026, the Company issued a press release announcing the entry into an Equity and Asset Purchase Agreement (the "Morgantown Purchase Agreement") for the Morgantown generating station in Charles County, Maryland... contemplates the acquisition of the Morgantown generating station, a grid-connected power generation facility with approximately 210 MW of current operational capacity... The Company expects to close on the Morgantown acquisition in the second quarter of 2026, subject to receiving these consents and approvals”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

delays TeraWulf 10-Q filed 2026-08-05

Quote: “On July 29, 2026, FERC authorized the pending acquisition of the Morgantown generating station.”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 2, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2026-02-27.
October 9, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.