The claim, verbatim

Completion of the Morgantown power generation facility acquisition is subject to regulatory approvals, including approval from the Federal Energy Regulatory Commission (FERC)

Source (primary)

TeraWulf 424B5 filed 2026-04-14 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “Completion of the transaction is subject to regulatory approvals, including approval from the Federal Energy Regulatory Commission ("FERC"), and there can be no assurance that such approvals will be obtained or that the transaction will be completed on the anticipated timeline or at all.”

How we checked this

Checked on September 15, 2026. The cited source supports every part of this claim.

The filing states that completing the Morgantown transaction requires regulatory approvals, including from FERC.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1083301/000110465926043250/tm2611661-3_424b5.htm) in full (221,842 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf 424B5 filed 2026-04-14

Quote: “Completion of the transaction is subject to regulatory approvals, including approval from the Federal Energy Regulatory Commission ("FERC"), and there can be no assurance that such approvals will be obtained or that the transaction will be completed on the anticipated timeline or at all.”

View cached copy (2026-08-31)Live source ↗