jain.com

HPC Expansion Capability Within 24 Months

Company: TeraWulf

Subject kind
facility capacity
Statement date
2025-05-08
Promised by
2027-05-09
Promised amount
400.0 MW
Current status
stated

The claim, verbatim

Ability to deliver approximately 400 MW of additional HPC capacity within the next 24 months

Source (primary)

Investor Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “Ability to deliver an incremental ~400 MW of capacity for HPC within the next 24 months”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The presentation states an ability to deliver an incremental ~400 MW of HPC capacity within the next 24 months.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_0c87b48cb4d1c6967968c7d0c3e5933d/terawulf/db/2396/23301/pdf/WULF_Q1_2025_Investor_Pres_vF.pdf) in full (23,307 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Investor Presentation

Quote: “Ability to deliver an incremental ~400 MW of capacity for HPC within the next 24 months”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2025-05-08.