Promised amount
7.2 USD/MW
Current status
stated

The claim, verbatim

Updated capex guidance of approximately $7.2M per critical MW for HPC infrastructure build

Source (primary)

Investor Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “CapEx per Critical MW ~$7.2M/MW”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The HPC cost-to-build slide lists updated guidance of CapEx per Critical MW of ~$7.2M/MW.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_0c87b48cb4d1c6967968c7d0c3e5933d/terawulf/db/2396/23301/pdf/WULF_Q1_2025_Investor_Pres_vF.pdf) in full (23,307 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Investor Presentation

Quote: “CapEx per Critical MW ~$7.2M/MW”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2025-05-08.