jain.com

Core42 HPC leases commenced

Company: TeraWulf

Subject kind
product
Statement date
2026-09-01
Promised amount
18.0 MW
Current status
stated

The claim, verbatim

Core42 Leases commenced in 2025 comprising 18 critical IT MW HPC lease capacity as of December 31, 2025

Source (primary)

View 10-K PDF (IR page (investors.terawulf.com), ir_release)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “Certain of the Core42 Leases commenced in 2025 which comprised 18 critical IT MW HPC lease capacity as of December 31, 2025”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms View 10-K PDF

Quote: “Certain of the Core42 Leases commenced in 2025 which comprised 18 critical IT MW HPC lease capacity as of December 31, 2025”

View cached copy (2026-09-01)Live source ↗Archive.org ↗