Asset retirement obligations
Company: TeraWulf
The claim, verbatim
TeraWulf's asset-retirement obligations at Hawesville total approximately $16.5 million as of June 30, 2026, for asbestos remediation and spent pot liner removal
Source (primary)
TeraWulf Advances $4B Data Center at Former Kentucky Smelter - Engineering News-Record (-, news_article)
View cached copy (2026-09-01)Live source ↗
Quote: “TeraWulf's filings identify asbestos remediation and spent pot liner removal as its primary asset-retirement obligations at Hawesville, totaling about $16.5 million as of June 30”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms TeraWulf Advances $4B Data Center at Former Kentucky Smelter - Engineering News-Record
Quote: “TeraWulf's filings identify asbestos remediation and spent pot liner removal as its primary asset-retirement obligations at Hawesville, totaling about $16.5 million as of June 30”