jain.com

Asset retirement obligations

Company: TeraWulf

Subject kind
regulatory
Statement date
2026-08-25
Promised amount
16.5 USD
Current status
stated

The claim, verbatim

TeraWulf's asset-retirement obligations at Hawesville total approximately $16.5 million as of June 30, 2026, for asbestos remediation and spent pot liner removal

Source (primary)

TeraWulf Advances $4B Data Center at Former Kentucky Smelter - Engineering News-Record (-, news_article)
View cached copy (2026-09-01)Live source ↗

Quote: “TeraWulf's filings identify asbestos remediation and spent pot liner removal as its primary asset-retirement obligations at Hawesville, totaling about $16.5 million as of June 30”

How we checked this

Checked on September 15, 2026. The cited source supports every part of this claim.

The article says TeraWulf's filings identify asbestos remediation and spent pot liner removal as its primary Hawesville asset-retirement obligations, totaling about $16.5 million as of June 30.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.enr.com/articles/63556-terawulf-advances-4b-data-center-at-former-kentucky-smelter) in full (11,913 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf Advances $4B Data Center at Former Kentucky Smelter - Engineering News-Record

Quote: “TeraWulf's filings identify asbestos remediation and spent pot liner removal as its primary asset-retirement obligations at Hawesville, totaling about $16.5 million as of June 30”

View cached copy (2026-09-01)Live source ↗