- Applied Digital — ~10% equity stake in Base Electron stated · 2026-10-08
- Applied Digital — ChronoScale 50 MW Microsoft AI compute deployment stated · 2026-10-08
- Applied Digital — $350K community grants in Oliver County stated · 2026-10-08
- Applied Digital — Ekso business held for sale stated · 2026-10-08
- Applied Digital — ~96% ownership of ChronoScale stated · 2026-10-08
- Applied Digital — Jamestown and Ellendale hosting at full capacity stated · 2026-10-08
- Applied Digital — Third PF1 building and other campuses under construction stated · 2026-10-08
- Applied Digital — Campus tenant assignments stated · 2026-10-08
- Applied Digital — 1.41 GW leased across five campuses stated · 2026-10-08
- Applied Digital — ~10% equity interest in Base Electron stated · 2026-10-08
- Applied Digital — Base Electron ~1,200 MW gas PPA stated · 2026-10-08
- Applied Digital — Finland up to ~1 GW power capacity stated · 2026-10-08
- Applied Digital — North Dakota delivered capacity 300 MW by end 2026 stated · 2026-10-08
- Applied Digital — Polaris Forge 1 Building 2 Phase 2 RFS stated · 2026-10-08
- Applied Digital — ChronoScale–Microsoft 50 MW GB300 deployment stated · 2026-10-08
- Applied Digital — $1.59B 7.000% Senior Secured Notes due 2031 stated · 2026-10-08
- Applied Digital — Polaris Forge 1 Building 2 Phase 1 RFS stated · 2026-10-08
- Applied Digital — Delta Forge 2 210 MW hyperscaler lease stated · 2026-10-08
- Applied Digital — Cash vs. liabilities at Aug 31, 2026 stated · 2026-10-07
- Applied Digital — Targets 15+ year leases with investment-grade tenants stated · 2026-10-07
- Applied Digital — Polaris Forge 1 fully leased stated · 2026-10-07
- Applied Digital — ~$36B contracted revenue stated · 2026-10-07
- Applied Digital — >80% of debt principal due FY2031 or later stated · 2026-10-07
- Applied Digital — Q1 FY2027 GAAP net loss stated · 2026-10-07
- Applied Digital — Q1 FY2027 adjusted EPS stated · 2026-10-07
- Applied Digital — Q1 FY2027 HPC Hosting segment revenue stated · 2026-10-07
- Applied Digital — Total debt vs cash at end of Q1 FY2027 stated · 2026-10-07
- Applied Digital — Polaris Forge HPC hosting ramp drives Q1 FY2027 revenue stated · 2026-10-07
- Applied Digital — 300 MW in North Dakota by end of 2026 stated · 2026-10-07
- Applied Digital — Expansion lease rates >15% higher stated · 2026-10-07
- Applied Digital — Over 80% of debt principal due fiscal 2031 or later stated · 2026-10-07
- Applied Digital — Closed $1.59B notes offering at 7% verified · 2026-10-07
- Applied Digital — Finland site initial power expected 2028 stated · 2026-10-07
- Applied Digital — Finland agreement for up to 1 GW of power stated · 2026-10-07
- Applied Digital — Contracted critical IT load portfolio stated · 2026-10-07
- Applied Digital — Finland spending tied to commercial and regulatory milestones stated · 2026-10-07
- Applied Digital — Polaris Forge 1 – ramp from 250 MW to 400 MW leased stated · 2026-10-07
- Applied Digital — Finland project – up to 1 GW power access stated · 2026-10-07
- Applied Digital — Net loss US$249.2m stated · 2026-10-07
- Applied Digital — Revenue US$611.3m stated · 2026-10-07
- Applied Digital — Polaris Forge 1 400 MW under lease stated · 2026-10-07
- Applied Digital — Finland initial power expected from 2028 stated · 2026-10-07
- Applied Digital — Finland project up to 1 GW power capacity stated · 2026-10-07
- Applied Digital — Base-term lease revenue from contracted portfolio stated · 2026-10-07
- Applied Digital — Contracted critical IT load across five campuses stated · 2026-10-07
- Applied Digital — Debt maturity profile verified · 2026-10-07
- Applied Digital — Cash balance at quarter end verified · 2026-10-07
- Applied Digital — Debt balance at quarter end verified · 2026-10-07
- Applied Digital — Expansion lease rate uplift stated · 2026-10-07
- Applied Digital — 250 MW placed in service past 12 months verified · 2026-10-07
- Applied Digital — Fiscal Q1 2027 net loss stated · 2026-10-07
- Applied Digital — Fiscal Q1 2027 base rent stated · 2026-10-07
- Applied Digital — Fiscal Q1 2027 revenue stated · 2026-10-07
- Applied Digital — Liquidity sufficient for at least 12 months stated · 2026-10-07
- Applied Digital — Q1 FY27 financing activities provided $1.54B stated · 2026-10-07
- Applied Digital — $3.7B cash and restricted cash as of Aug 31, 2026 stated · 2026-10-07
- Applied Digital — $6.4B debt as of Aug 31, 2026 stated · 2026-10-07
- Applied Digital — ~$36B contracted revenue across five campuses stated · 2026-10-07
- Applied Digital — 250 MW placed into service over prior 12 months stated · 2026-10-07
- Applied Digital — Macquarie Asset Management preferred equity stated · 2026-10-07
- CoreWeave — FY2026 revenue outlook raised to $12.4B–$13.2B stated · 2026-10-07
- CoreWeave — $2.6B GPU-backed loan terms stated · 2026-10-07
- CoreWeave — Renewal or re-lease of customer contracts backing $2.6B loan stated · 2026-10-07
- CoreWeave — CoreWeave FY2026 revenue guidance raised stated · 2026-10-07
- CoreWeave — Customer contracts backing $2.6B loan average three years stated · 2026-10-07
- CoreWeave — Cash trap/sweep provisions in $2.6B loan stated · 2026-10-07
- CoreWeave — $3.1B facility completed in May stated · 2026-10-07
- CoreWeave — $2.6B AI infrastructure loan stated · 2026-10-07
- Applied Digital — 3.5-4 GW capacity by end of 2030 stated · 2026-10-07
- Applied Digital — ~2 GW capacity by end of 2028 stated · 2026-10-07
- Applied Digital — Base Electron 1,200 MW gas plant power deal stated · 2026-10-07
- Applied Digital — Lease rates could rise >15% stated · 2026-10-07
- Applied Digital — Macquarie preferred equity plus project debt for new campuses stated · 2026-10-07
- Applied Digital — Polaris Forge 3, Delta Forge 1 & 2 leased to hyperscaler stated · 2026-10-07
- Applied Digital — North Dakota to reach 300 MW by end of 2026 verified · 2026-10-07
- Core Scientific — Malikie patent dispute dismissed stated · 2026-10-07
- Nebius — US$2b capital expenditure in 2025 stated · 2026-10-07
- Nebius — 1 GW of power secured by 2026 stated · 2026-10-07
- Nebius — Microsoft contract worth US$17.4b stated · 2026-10-07
- Applied Digital — Total debt at Aug 31, 2026 stated · 2026-10-07
- Applied Digital — Cash and restricted cash at Aug 31, 2026 stated · 2026-10-07
- Applied Digital — Leased critical IT load across campuses stated · 2026-10-07
- Applied Digital — Polaris Forge 1 live campus capacity stated · 2026-10-07
- Applied Digital — Polaris Forge 1 Building 2 second 75 MW phase delivered stated · 2026-10-07
- Nebius — 1 GW power target by 2026 stated · 2026-10-07
- Nebius — 2025 capital expenditure commitment stated · 2026-10-07
- Nebius — Microsoft contract stated · 2026-10-07
- Nebius — Eigen AI acquisition stated · 2026-10-07
- CoreWeave — $2.6B loan with Cash Trap Event clause stated · 2026-10-07
- CleanSpark — CleanSpark Sandersville AI infrastructure lease stated · 2026-10-07
- Applied Digital — Finland site hyperscaler discussions stated · 2026-10-07
- Applied Digital — Finland campus initial power in 2028 stated · 2026-10-07
- CoreWeave — Neural AI subpoena action against non-party CoreWeave dismissed stated · 2026-10-07
- CoreWeave — Three Indonesia facilities (360 MW) online in 2028 stated · 2026-10-07
- CoreWeave — Several-billion-dollar India investment stated · 2026-10-07
- Applied Digital — 1.7 GW operational/contracted, 1.3 GW under development stated · 2026-10-07
- Applied Digital — 1,410 MW contracted critical IT load, ~$36B base-term lease revenue stated · 2026-10-07
- Applied Digital — Finland AI Factory campus, up to 1 GW, initial power from 2028 stated · 2026-10-07
- Applied Digital — Polaris Forge 1 reaches 250 MW operational verified · 2026-10-07
- Applied Digital — Additional 75 MW phase delivered, 250 MW operational stated · 2026-10-07