Hansford County wind farm - nameplate wind capacity
Company: Marathon Digital
The claim, verbatim
Company acquired wind farm in Hansford County, Texas with 240 MW of interconnection capacity and 114 MW of nameplate wind capacity
Source (primary)
Marathon Digital 10-K filed 2026-03-02 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “We acquired a wind farm in Hansford County, Texas, with 240 MW of interconnection capacity and 114 MW of nameplate wind capacity to establish a behind-the-meter data center at low energy costs”
How we checked this
Checked on September 16, 2026. The cited source supports every part of this claim.
The 10-K reports the Hansford County wind farm acquisition with both the 114 MW nameplate and 240 MW interconnection figures.
Confirmed in the source:
- MARA acquired a wind farm in Hansford County, Texas
- The wind farm has 114 MW of nameplate wind capacity
- The wind farm has 240 MW of interconnection capacity
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1507605/000150760526000007/mara-20251231.htm) in full (412,365 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Marathon Digital 10-K filed 2026-03-02
Quote: “We acquired a wind farm in Hansford County, Texas, with 240 MW of interconnection capacity and 114 MW of nameplate wind capacity to establish a behind-the-meter data center at low energy costs”