Promised amount
225.0 MW
Current status
stated

The claim, verbatim

East Ohio region facilities collectively support approximately 225 MW of total capacity

Source (primary)

Marathon Digital 10-K filed 2026-03-02 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “Our East Ohio region includes facilities across two cities that operate as grid connected sites and collectively support approximately 225 MW of total capacity.”

How we checked this

Checked on September 16, 2026. The cited source supports every part of this claim.

The filing states the East Ohio facilities collectively support approximately 225 MW.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1507605/000150760526000007/mara-20251231.htm) in full (412,365 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Marathon Digital 10-K filed 2026-03-02

Quote: “Our East Ohio region includes facilities across two cities that operate as grid connected sites and collectively support approximately 225 MW of total capacity.”

View cached copy (2026-08-31)Live source ↗