Central Ohio facility capacity

Company: Marathon Digital

Subject kind
facility capacity
Statement date
2026-09-01
Promised amount
150.0 MW
Current status
stated

The claim, verbatim

Central Ohio grid connected facility contributes 150 MW of capacity

Source (primary)

View 10-K PDF (IR page (ir.mara.com), ir_release)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “In Central Ohio, our grid connected facility contributes an additional 150 MW, further strengthening our overall capacity footprint.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms View 10-K PDF

Quote: “In Central Ohio, our grid connected facility contributes an additional 150 MW, further strengthening our overall capacity footprint.”

View cached copy (2026-09-01)Live source ↗Archive.org ↗